Gonneville PGM-Nickel-Copper-Cobalt Project

Project Overview

The Gonneville Platinum Group Metals-Nickel-Copper-Cobalt (PGM-Ni-Cu-Co) is a mine development project located on Chalice-owned farmland, ~70km north-east of Perth in Western Australia.

A shallow, tier-1 scale polymetallic Resource was discovered by Chalice’s geologists in early 2020. The
PGM-nickel-copper dominated Resource is one of the largest of its type in the western world and is one of
the few amenable to open-pit mining.

The Resource hosts a rare mix of critical and strategic minerals, such as palladium, platinum, nickel, copper
and cobalt, which are vital inputs into the auto sector (electric, hybrid and internal combustion engine
vehicles), the defence sector (high performance materials and electronics), data centres (semiconductors
and electrical components), as well as many rapidly growing decarbonisation applications.

In December 2025, a Pre-Feasibility Study was completed which determined the optimal development pathway for the Project. The PFS describes a two-stage, open-pit critical minerals mine and process plant development which is predicted to become a large-scale producer of palladium, nickel and copper (co-products) over a
modelled open-pit life of 23yrs, with valuable byproducts from cobalt, platinum and gold. The PFS has
robust financial metrics which underpin the development of the Project at conservative long-term price
assumptions.

The Project is favourably located, with access to established road, rail, port and high-voltage power infrastructure nearby, plus access to a significant ‘residential’ mining workforce in the Perth surrounds.

In 2024, the Western Australian and Commonwealth Governments awarded ‘Strategic Project’ and ‘Major Project’ status to the Project, recognising its scale and strategic importance to the development of Australia’s critical minerals industry.

The Project has been significantly de-risked, with an investment of ~$270 million (to end FY26) by Chalice since the discovery in 2020. The Company is continuing to progress regulatory approvals, remaining studies, offtake and financing of the project ahead of a targeted Final Investment Decision (FID) in H1 CY28.

Location

~70km NE of Perth, Western Australia

Project Stage

Pre-Feasibility; Permitting

Acquired

Exploration licenses staked in 2018

Ownership

100%

Chalice is proud to be part of the local community
surrounding the Gonneville Project

We are committed to prioritising local employment, supporting local businesses and investing locally to
create long lasting benefits. For more detail on the Project proposal and the approvals processes, visit the
Community Hub.

What Gonneville means for Western Australia

$24.1 billion. 3,761 jobs – One project

Independant modelling puts the Gonneville PGM-Nickel-Copper-Cobalt Project’s contribution to WA’s economy at $24.1 billion.

Explore the full economic impact of the Gonneville project

Metals we will produce

The Gonneville Resource hosts a rare mix of critical minerals required for decarbonisation and urbanisation. Large-scale deposits like Gonneville are very rare and therefore have high strategic value, as current production of platinum group metals is dominated by Russia and South Africa and significant supply shortages are predicted.

Palladium

13Moz contained in Resource

Platinum

3Moz contained in Resource

Nickel

960 kt contained in Resource

Copper

540 kt contained in Resource

Cobalt

96 kt contained in Resource

Gold

0.5Moz contained in Resource

Production Profile

Gonneville will have a significant production profile, producing 220koz of precious metals, 7kt of nickel, 8kt of copper and 700t of cobalt per annum for 23 years.

Financial Metrics

The Gonneville Pre-Feasibility Study completed in December 2025 confirmed Gonneville as the largest and lowest cost Project of its type in the western world. It is on track to become a world-class, long-life, low-cost critical minerals mine with compelling financial metrics at bottom-of-the-cycle commodity price assumptions.

Table 1. Gonneville Mineral Resource Estimate (Resource) 23 April 2024

Mass

GRADE

Contained Metal

Classification

Mt

3E (g/t)

Ni (%)

Cu (%)

Co (%)

3E (Moz)

Ni (kt)

Cu (kt)

Co (kt)

Measured

2.9

1.20

0.21

0.17

0.018

0.12

6.1

4.8

0.52

Indicated

400

0.79

0.15

0.087

0.015

10

610

370

65

Inferred

250

0.80

0.15

0.076

0.014

6.4

370

200

37

Total

660

0.79

0.15

0.083

0.015

17

960

540

96

Within pit constrained cut-off of A$25/t NSR and underground MSO cut-off of A$110/t NSR.

The Gonneville Deposit is located within a ~1.9km x 0.9km x >0.8km section of the Julimar Complex, known as the Gonneville Intrusion, which has a north-north-east strike, maximum thickness of approximately 650m, and 45° west-north-west dip.

The Gonneville Intrusion is composed predominantly of serpentinised olivine peridotite / harzburgite (serpentine-magnetite-amphibole-chromite) with lesser intervals of pyroxenite (amphibole-chlorite), gabbro and leucogabbro (clinozoisite-amphibole) divided into a series of eight litho-geochemical domains.

The weathering profile in the area extends to approximately 30–40m below surface. A well-developed laterite and saprolite profile is present which contains elevated palladium grades from near surface to a depth of approximately 25m.

The litho-geochemical domains broadly parallel the strike and dip of the Gonneville Intrusion and are interpreted to represent discrete magma influxes and associated fractionation units. The intrusion is crosscut by a later granite body, which broadly parallels the dip and strike orientation of the mafic-ultramafic package.

660 Mt

Total Mineral Resource

17 Moz 3E

Contained in Resource

260 Mt

Total Ore Reserve

7.1 Moz 3E

Contained in Reserve

Table 1. Gonneville Mineral Resource Estimate (Resource) 23 April 2024

Mass

Grade

Contained Metal

Classification

Mt

3E (g/t)

Ni (%)

Cu (%)

Co (%)

3E (Moz)

Ni (kt)

Cu (kt)

Co (kt)

Measured

2.9

1.20

0.21

0.17

0.018

0.12

6.1

4.8

0.52

Indicated

400

0.79

0.15

0.087

0.015

10

610

370

65

Inferred

250

0.80

0.15

0.076

0.014

6.4

370

200

37

Total

660

0.79

0.15

0.083

0.015

17

960

540

96

Within pit constrained cut-off of A$25/t NSR and underground MSO cut-off of A$110/t NSR.

Table 2. Gonneville Ore Reserve Estimate (Reserve)

Mass

Grade

Contained Metal

Classification

Mt

3E (g/t)

Ni (%)

Cu (%)

Co (%)

3E (Moz)

Ni (kt)

Cu (kt)

Co (kt)

Proved

2.5

1.40

0.22

0.18

0.018

0.11

5.4

4.4

0.45

0.85

0.85

0.85

0.16

0.098

0.017

7.1

400

250

43

Total

260

0.86

0.16

0.098

0.017

7.1

400

260

43

Within pit constrained cut-off of A$100-110/t NSR and underground cut-off of A$110/t NSR.

For further details, refer to the Company’s ASX Announcement “Gonneville PGM-Ni-Cu-Co Project PFS” dated 8 December 2025.

Development Plan

The development plan for the Project includes an open-pit mine, process plant and supporting infrastructure, constructed in two stages. Stage 1 is designed for the lowest initial capital cost, maximum rate of return and shortest capital payback period, while the Stage 2 expansion is designed for optimal strategic value, mine life and profitability through the price cycle

Stage 1

Years 1–4

1 Mtpa

Oxide processing

4 Mtpa

Sulphide processing

  • Scoped for lowest capital cost, maximum rate of return and shortest capital payback period.
  • 4 years of higher-grade and higher-margin open-pit mining, processing oxide and sulphide in parallel, through a conventional crush-grind-flotation-leach process plant.

Stage 2

Years 5+

12 Mtpa

Sulphide processing

14 Mtpa

Ultimate sulphide throughput

  • Expansion optimised for optimal strategic value, mine life and
    profitability through the price cycle.
  • A long-life, bulk open-pit mining phase. De-bottlenecking of the process plant is completed post oxide feed exhaustion in year 9 to allow for an ultimate 14Mtpa sulphide process throughput rate.

The staged development approach de-risks the project with efficient deployment of capital and ability to adapt future stages to learnings and macro-economic conditions. The investment decision for the Stage 2 expansion is expected to be made separately to Stage 1 FID, in ~2031-2033.

Development Timeline

The PFS has demonstrated that the Project is technically and commercially viable, and hence Chalice is now progressing the development plan into a Feasibility Study (FS). The FS will involve optimising the design and undertaking detailed engineering to prepare the Project for a Final Investment Decision (FID) on Stage 1, targeted in H1 CY28.

DEC 2025
Pre-Feasibility
Study completed
H2 CY27
Feasibility Study
completed
H2 CY27
Offtake
agreements
executed
H1 CY28
Funding sourced
H1 CY28
Major
environmental
approvals
H1 CY28
Final Investment
Decision, Stage 1
EARLY 2030
First production