About the approvals processes
The Gonneville PGM-Nickel-Copper-Cobalt Project is a critical minerals mine development containing palladium, platinum, nickel, copper and cobalt. These critical minerals are essential for technologies that will help address climate change and supply is predicted to fall short of future demand.
Before a mine can be developed, the Project must receive the approval of State and Commonwealth Governments, subject to a comprehensive environmental assessment to evaluate details of the proposed mine and infrastructure corridors; the potential environmental impacts, and how these impacts will be avoided, mitigated and managed.
The Project is in the engineering studies and approvals stage. Chalice has chosen to complete approvals processes alongside ongoing engineering studies to ensure community feedback and environmental considerations can be incorporated early in the Project plans. The approvals process and further studies are expected to take approximately three years to complete.
Project Stage

Approvals Update – October 2026
Since lodging our environmental referral in March 2024, we’ve continued to optimise the Gonneville Project design – with additional environmental surveys, technical modelling and stakeholder feedback.
That work has paid off. Total clearing across the mine site, is now capped at 746 hectares, down from 940 hectares in our original 2024 proposal – a reduction of 194 hectares, or 21%. Options for water and power infrastructure have been consolidated into a single preferred alignment – reducing the overall disturbance footprint. A solar farm and battery will supplement our grid connection for power generation, reducing the Project’s greenhouse gas emissions profile.
We have submitted these changes to the Environmental Protection Authority (EPA) as a Section 43A amendment to our Environmental Referral – a normal part of the approvals process. The amendment will be available in full on the EPA website, with public comment open from 23 October – 5 November 2026.
The Section 156A variation submitted to the Commonwealth has been accepted, with the decision to be published on the EPBC Act Public Portal. We’ll keep sharing updates here as the approval process progresses.
If approved, the Gonneville PGM-Nickel-Copper-Cobalt Project would mine and process ore that would be transported to domestic or overseas customers for further refinement into end-use metals. The proposed Project includes:
Mine Development Area
- Open pit and underground mining operations.
- Ore processing.
- Tailings storage facilities, stockpiles and waste rock landforms.
- Supporting infrastructure e.g. offices, workshops, water treatment plant and internal haul roads.
- Temporary facilities during construction e.g. accommodation and water supply.
These elements will be contained within a 2,240ha (~22.4km2) development area on farmland owned by Chalice. This land is already 56% cleared from previous agricultural use.
Infrastructure Corridor
The Project also includes options for off-site infrastructure corridors for water pipelines and power lines. Multiple corridor options are being considered and investigated in consultation with government and other stakeholders.
Transportation corridors are still in design phase with road and/or existing rail infrastructure options being considered.

How are environmental impacts assessed?
The Proposal will be assessed in accordance with the State Environmental Protection Act 1986 and the
Commonwealth Environment Protection and Biodiversity Conservation Act 1999.

Chalice has undertaken extensive field studies since 2020 to understand the environmental considerations of the Project area, including:
- Surveys of flora, fauna and vegetation to gather information about the diversity, health and location of species. This has included surveys for threatened and priority species such as black cockatoo and chuditch, and native vegetation studies.
- Studies of surface and ground water resources to understand the water quality, quantity and movements.
- Archaeological and ethnographic cultural heritage surveys conducted by Whadjuk Traditional Owners.
- Field investigations took place during Spring 2025 where Chalice engaged independent consultants to contact private landholders along potential water and power infrastructure corridors seeking information to support land access.
Chalice will prepare an Environmental Review Document (ERD) that will provide details of the proposed mine and its potential environmental impacts, and details of the studies completed by Chalice. The ERD will be made available for the community to review and comment on as the Project develops.